Gym Shed

Steps

About six weekends plus a week for the slab to cure. Don't go past a hold point until it's done. Ticks save on this device.

Before you dig

Week 00 of 8

Set out and dig

Weekend 10 of 6

Film and steel

Weekend 10 of 5

Pour and cure

One morning, then 7 days0 of 4

Wall frames

Weekends 2 and 30 of 7

Roof

Weekends 3 and 40 of 6

Close in

Weekends 4 and 50 of 3

Power and lining

Weekends 5 and 60 of 5

Finish and fit-out

Weekend 60 of 4

Good to know

  1. Not engineered. The frame follows common practice for a small timber shed in an N2 wind area, and the slab follows common practice for small slabs on reactive clay. Before you buy, show the frame sheets to your timber yard or check them against the AS 1684 span tables. On an exposed site (N3), add a strap over every rafter and stud ties beside each opening.
  2. Height. The high-side capping finishes 2,875 above the slab. The limit is 3,000 above natural ground, so the slab can sit at most 125 above the lowest natural ground along the back wall. On a flat site 100 works. If the ground falls toward the back, take the difference off every stud and plate height.
  3. Clay. If the ground cracks open in summer (very reactive clay), take the edge beams to 450 deep and keep garden beds and sprinklers away from the slab edge.
  4. Doors and windows. The openings suit a pair of 820 doors in a prehung frame and 1,210 × 600 sliders. Buy them first, then adjust the rough openings.
  5. Lining. Studs and rafters sit at 600 so the edges of 1,200 wide ply sheets land on them. Trim the first sheet on each wall to make that work.
  6. Colorbond. Cut it with snips or a nibbler, never a grinder. Sweep up the swarf every day or it rusts into the paint.
  7. Treated pine. Wear a P2 mask when cutting, brush preservative on H3 cut ends, and never burn offcuts.
  8. Concrete day. Have the formwork, film, mesh and helpers ready the day before. The truck only gives you a short unloading window.